Ferdinand Officials Defend Handling of Zoning, Utility Matters Amid Controversy
At this week’s meeting of the Ferdinand Board of Zoning Appeals, a joint report from town
officials sought to clarify past decisions and address allegations of impropriety.
Ferdinand town officials are defending the town’s handling of the development process at 835
Main Street attracting public scrutiny. Board member Don Farina resigned his position prior to
the meeting as a result of the conflict. Ferdinand Town Council President Ken Sicard presented
a report to the board regarding questions being raised about utility permit and zoning matters
involving the BZA. It was filed jointly by Sicard in his role as Council President, BZA Chairman
Mark Dilger, and Plan Commission President Brett Schipp.
The procedural requirements for the BZA and Plan Commission were reviewed, in addition to
other documentation including town records, meeting minutes, recordings, correspondence,
building code requirements, and a health department inquiry. The review concluded that all
required procedural steps were met in approving the property's rezoning and variance for a
proposed five-unit apartment building.
Additionally, Sicard said the review found that a stop-work notice previously posted at the
property under the BZA vice chairman's title was issued without authorization from the BZA or
the Town Council. The notices were subsequently removed and replaced with notices
personally signed by Sicard.
The property, formerly a restaurant, was rezoned from commercial to multifamily residential in
May 2023, prior to the property purchase, following favorable recommendations from the Plan
Commission and Town Council. The variance also established several conditions, including
driveway approval from INDOT, approval by the State Fire Marshal for compliance with state
building codes, and requirements for off-site parking.
The report also addressed questions about whether the five variance conditions must be
completed before construction can proceed. Officials concluded the conditions must be
satisfied before apartments are rented, contingent upon the building passing its final State Fire
Marshal inspection. The developer is still addressing the driveway approval and parking
requirements, while construction is proceeding under a state-issued construction design
release.
The report further defended the town's notification process, stating that certificates of mailing
were provided for notices sent to six affected property owners. The report said some nearby
property owners said that they never received these mailing, and insinuated that they were
never sent, but that could not be substantiated. Officials said the town is entitled to rely on
USPS records as proof of timely mailing.
Two utility-related concerns were also addressed. One involved a water main break at 521 East
21st Street. The town said its Water and Sewer Department repaired the break and restored
the affected area, while the homeowners received an adjustment for water used during
cleanup.
The other involved relocating a waterline on East 20th Street after a property owner discovered
the pipe was not where town maps indicated during pool installation. The town said the
existing asbestos-cement line from the 1960s was already scheduled for replacement. Under an
arrangement approved by the Town Council in June 2025, the property owner covered material
costs while the town provided labor.
Sicard concluded that the developer followed the appropriate steps for construction, and the
town followed its ordinances and established procedures.
In other business, members were informed that the Town Council had established a temporary
moratorium on large solar, battery energy storage system (BESS) and data center projects. The
pause will allow the Plan Commission time to develop appropriate regulations for facilities not
addressed in the town's existing zoning ordinance, originally adopted in 1997.
For more information on these and other updates, visit www.ferdinandindiana.org
- Drew Hasselbring